After a month of delays, crews begin resurfacing Spring, Cannon streets

CHARLESTON, SC (WCSC) - A process of resurfacing of Spring and Cannon Streets in downtown Charleston began Monday, months after the original planned start date.

Work was set for December, but it got delayed until late January. By then, as the milling process began, a contractor convinced the city it would be wise to wait until early Spring.

The resurfacing is expected to last six days, according to city officials.

One lane of eastbound traffic on Cannon and one lane of westbound traffic on Spring will remain open. Traffic will be diverted into the parking lanes, which means parking will not be allowed on the streets during the construction.

The work will take place during daylight hours beginning at 7 a.m. The construction schedule can be found below:

  • Monday:
    • No parking on Spring Street.
    • Spring Street: Milling south side (Coming to President).
  • Tuesday:
    • No parking on both Cannon and Spring Streets.
    • Spring Street: Paving south side.
    • Cannon Street: Milling north side.
  • Wednesday:
    • No parking on both Cannon and Spring Streets.
    • Spring Street: Milling north side (Meeting to President).
    • Cannon Street: Paving north side.
  • Thursday:
    • No parking on Spring Street until pavement markings are in place.
    • No parking on Cannon Street.
    • Spring Street: Paving north side.
    • Cannon Street: Milling south side.
  • Friday:
    • No parking on Cannon Street until pavement markings are in place.
    • No parking on Spring Street within work zone. As pavement markings are installed, parking will be opened.
    • Cannon Street: Finish milling south side. Begin paving south side.
    • Spring Street: Complete pavement markings. Intersection work may be completed as needed.
  • Saturday and/or March 12:
    • Cannon Street: Finish paving south side. Intersection work may be completed as needed.
    • No parking on Cannon Street within work zone. As pavement markings are installed, parking will be opened.